HR/Payroll Replacement Status Report — April 2014

At the CFO meeting in February, we received direction that we should follow a formal and open process for the evaluation and selection project (as opposed to selecting from an existing state contract).  Following that meeting we have met with TAMU System procurement on several occasions and have decided to proceed with an RFP approach.  Additional guidance at the CFO meeting was that we should focus our efforts in the HR/Payroll area.  So it is our intention to not provide detail requirement for finance in the RFP, but to simply ask the vendors to provide general information on their financial offering and how it will integrate with their HR/Payroll proposal.

Additionally in February we completed the assessment conducted by Workday.  We thank all of you who participated in those meetings.  We will share the results of that assessment with you as we move forward and define our requirements.

As Carol and I have worked to push this project forward, we have been encumbered by our other duties.  To assist with resources and provide overall guidance to the process, we have decided to engage a consultant to help develop and push out the RFP.  We are in discussions with one who has specific experience with Texas higher education.  We hope we can agree to a statement of work by the end of next week.  We are excited to get the help and the guidance.

Over the next two weeks Carol Manthei will be contacting several of you to participate in working group meetings to define and review our requirements.  The consultant we engage will bring base requirements for higher education which should expedite this process.  The work will primarily be done in May and June as we plan on sending out the RFP in mid-July.  We also expect the consultant to provide a web-based collaboration tool that will allow all of you, as well as other stakeholders, to participate and give feedback.  Also, Carol and I have shifted her duties and expect her to dedicate 75% of her time to this project until its completion.

Note also that we plan on having meetings for both the Steering Committee and Advisory groups in early May.

Several have still asked why we are proceeding down this path without a clear funding strategy.  In the judgment of TAMU System leadership, knowing the cost of a solution and having a clear understanding of the value it will provide will provide the business case to acquire the funding.

We have also adjusted the project timeline.  We now propose the following timeline, and feel that it is realistic and achievable.

ACTIVITY TARGET START DATE TARGET COMPLETE DATE
Contract with an ERP Selection Consultant April 23, 2014
Form internal project team April 15 April 30
Project start-up/planning with consultant April 23, 2015 April 30, 2014
Define business processes/Document requirements May 1 ,2014 June 30, 2014
Create RFP, attain approvals July 1, 2014 July 15, 2014
Issue RFP – receive vendor responses July 15, 2014 August 15, 2014
Determine short list (extended time due to FY end) August 15, 2014 Sept 15, 2014
Schedule/prep vendor demos Sept 15, 2014 Sept 30, 2014
Vendor Demonstrations/review alternatives October 1, 2014 October 31, 2014
Determine recommendation Nov. 1, 2014 Nov. 15, 2014
Advisory Group: Report recommendation to Steering Committee November 15, 2014
Steering Committee: Review recommendation and make decision November 15, 2014 December 1, 2014
Determine Funding Plan December  1, 2014 December 31, 2014

 

  • Home
  • News You Can Use
    • Announcements
    • What Project Helios Means to Me
  • What’s Happening
Texas A&M University System

Copyright © 2019 Texas A&M University System All rights reserved.

The Texas A&M University System · 301 Tarrow (map) · College Station, TX 77840 · Phone: (979) 458-7700 · email: tamus-webmaster@tamus.edu

 

State of Texas · Texas Homeland Security · Texas Veterans Portal · Risk, Fraud & Misconduct Hotline · Compact with Texans · Privacy · Web Accessibility · Reports